Factory handbookH02 · Formulas

Shop-floor formulas

The calculations a production head, a quality engineer and a maintenance in-charge reach for most often. Each one has the formula in full, an example you can check by hand, and a calculator. For OEE itself, see the OEE calculator and guide.

Last reviewed · Deda Systems engineering team, Chennai

Planning

Takt time

Takt time is the pace at which you must finish one unit to meet customer demand. It is set by the customer, not by the machine. Takt is a German word for a precise interval of time, like the beat in music.

Takt time = Available production time ÷ Customer demand

Example. A line has 450 minutes of available time in a shift and the customer needs 300 units per shift. Takt time = 450 ÷ 300 = 1.50 minutes per unit, or 90 seconds per unit.

Takt time, cycle time and lead time are three different things. Takt time is the target pace that demand requires. Cycle time is how long one part or one operation actually takes, measured on the floor. Production lead time is how long a product takes to move through the whole process from start to finish, including the time it spends waiting. If cycle time is longer than takt time, the line cannot meet demand without overtime.

Takt time calculator
Takt time
90 seconds per unit
In minutes
1.50 minutes per unit

Quality

First pass yield and rolled throughput yield

First pass yield (FPY) is the share of units that go through a process step correctly the first time, with no scrap and no rework. Rolled throughput yield (RTY) is the chance that a unit passes every step in a row without a defect.

FPY = (Units entering − Defective units) ÷ Units entering

RTY = FPY of step 1 × FPY of step 2 × … × FPY of the last step

Example. 500 parts enter an operation and 35 are scrapped or reworked. FPY = (500 − 35) ÷ 500 = 93.0%. A part then passes through four operations with first pass yields of 98%, 95%, 99% and 97%. RTY = 0.98 × 0.95 × 0.99 × 0.97 = 89.4%.

RTY can never be higher than the weakest step, and is usually lower. A plant whose final inspection passes 99% of parts can still have a low RTY if rework is happening quietly at every stage.

Yield calculator
First pass yield
93.0%
Rolled throughput yield
89.4%

Quality

DPMO (Defects per million opportunities)

DPMO lets you compare the defect rate of a simple part with that of a complex one, by counting how many chances for a defect each unit has.

DPMO = Defects ÷ (Units × Opportunities per unit) × 1,000,000

Example. An inspector finds 18 defects in 1200 assemblies. Each assembly has 5 characteristics that are checked. DPMO = 18 ÷ (1200 × 5) × 1,000,000 = 3000.

A caveat on “six sigma = 3.4 DPMO”. The 3.4 figure assumes the process mean drifts by 1.5 standard deviations over the long term. That shift is a convention from the Six Sigma method, not a law of statistics. Without it, limits at six standard deviations correspond to about 0.002 defects per million.

DPMO calculator
DPMO
3000

Quality

Process capability: Cp and Cpk

Cp compares the width of the tolerance with the natural spread of the process. Cpk does the same but also accounts for how far the process is off-centre, so Cpk is never larger than Cp.

Cp = (USL − LSL) ÷ 6σ

Cpk = the smaller of (USL − mean) ÷ 3σ and (mean − LSL) ÷ 3σ

USL and LSL are the upper and lower specification limits. σ is the process standard deviation.

Example. A shaft diameter is specified as 25.00 ± 0.05 mm, so USL = 25.05 and LSL = 24.95. A study gives a mean of 25.01 mm and a standard deviation of 0.012 mm. Cp = 0.10 ÷ (6 × 0.012) = 1.39. Cpk = the smaller of 1.11 and 1.67 = 1.11.

What number is required? That is set by your customer. A Cpk of at least 1.33 is a very common requirement, and 1.67 is commonly asked for on critical characteristics. The automotive PPAP manual published by AIAG uses 1.33 and 1.67 as the bands for judging initial process studies. Always check the customer-specific requirement.

Two conditions. Capability indices only mean something when the process is stable (in statistical control) and the data are roughly normally distributed. Pp and Ppk use the same formulas with the overall standard deviation of all the data, while Cp and Cpk use the short-term variation within subgroups.

Cp and Cpk calculator
Cp
1.39
Cpk
1.11
Upper side
1.11
Lower side
1.67

Maintenance

MTBF, MTTR and availability

MTBF (mean time between failures) says how long a machine runs between breakdowns. MTTR (mean time to repair) says how long a breakdown takes to fix. Together they give the machine’s inherent availability.

MTBF = Total operating time ÷ Number of failures

MTTR = Total repair time ÷ Number of repairs

Inherent availability = MTBF ÷ (MTBF + MTTR)

Example. In a month a press runs for 400 hours and breaks down 5 times. The repairs take 10 hours in total. MTBF = 400 ÷ 5 = 80.0 hours. MTTR = 10 ÷ 5 = 2.00 hours. Inherent availability = 97.6%.

This is not the availability in OEE. Inherent availability counts only breakdowns and repairs. OEE availability also counts changeovers and waiting for material. MTBF is also not a prediction of machine life: it describes failures during normal operation. For parts that are replaced and not repaired, the equivalent measure is MTTF (mean time to failure).

MTBF and MTTR calculator
MTBF
80.0 hours
MTTR
2.00 hours
Inherent availability
97.6%

Capacity

TEEP (Total effective equipment performance)

TEEP measures a machine against every minute of the calendar, where OEE measures it only against the time it was planned to run. It shows how much capacity is still unused before you invest in another machine.

Utilisation = Planned production time ÷ All calendar time

TEEP = OEE × Utilisation

Example. A machine runs one shift with 420 minutes of planned production time in a 1440-minute day, at 76.4% OEE. Utilisation = 420 ÷ 1440 = 29.2%. TEEP = 76.4% × 29.2% = 22.3%.

TEEP calculator
Utilisation
29.2%
TEEP
22.3%

Summary

All the formulas in one table

MeasureFormulaAnswers the question
OEEAvailability × Performance × QualityHow much of planned time made good parts at full speed?
Availability (OEE)Run time ÷ Planned production timeHow much of planned time was the machine running?
Performance (OEE)(Ideal cycle time × Total count) ÷ Run timeWas it running at full speed?
Quality (OEE)Good count ÷ Total countWere the parts right the first time?
TEEPOEE × (Planned production time ÷ Calendar time)How much total capacity is used?
Takt timeAvailable production time ÷ Customer demandHow fast must we finish each unit?
First pass yield(Units in − Defective units) ÷ Units inHow many were right with no rework?
Rolled throughput yieldProduct of the FPY of every stepWhat is the chance of passing every step cleanly?
DPMODefects ÷ (Units × Opportunities) × 1,000,000How does the defect rate compare across products?
Cp(USL − LSL) ÷ 6σIs the process spread narrow enough for the tolerance?
Cpkmin[(USL − mean) ÷ 3σ, (mean − LSL) ÷ 3σ]Is it narrow enough and centred?
MTBFOperating time ÷ Number of failuresHow long between breakdowns?
MTTRRepair time ÷ Number of repairsHow long does a breakdown take to fix?
Inherent availabilityMTBF ÷ (MTBF + MTTR)What uptime do breakdowns alone allow?

Sources

Where this comes from

The formulas and definitions on this page are the standard published ones. These are the references we checked them against. If you find an error, write to deep@deda.systems and we will correct it.

FAQ

Questions people ask

How do you calculate takt time?

Divide the available production time by customer demand for the same period. With 450 minutes available and a demand of 300 units, takt time is 1.5 minutes, or 90 seconds, per unit.

What is the difference between takt time and cycle time?

Takt time is the pace customer demand requires. Cycle time is the time an operation actually takes, measured on the floor. When cycle time is longer than takt time, the process cannot meet demand in the available time.

What is the difference between Cp and Cpk?

Cp compares the tolerance width with the process spread and ignores where the process is centred. Cpk also accounts for centring, by taking the distance from the mean to the nearer specification limit. Cpk equals Cp only when the process is exactly centred.

What Cpk value is acceptable?

Your customer sets the requirement. A minimum Cpk of 1.33 is common, with 1.67 often required for critical characteristics. The AIAG PPAP manual uses 1.33 and 1.67 as the bands for judging initial process studies.

Is MTBF the same as machine life?

No. MTBF is operating time divided by the number of failures for equipment that is repaired and returned to service. It describes how often failures occur, not how long the machine will last.

What is the difference between FPY and RTY?

First pass yield measures one process step. Rolled throughput yield multiplies the first pass yields of every step, giving the probability that a unit passes the entire process with no defect and no rework.

Also see

Next step

Want these numbers live?

Everything on this page can be done on paper. When you want it captured at the machine and on a screen during the shift, that is what we build. Thirty minutes on a call is usually enough to tell whether it is worth doing.

30 min
Free first call, with an engineer
2–4 days
On your floor before any proposal
Week 1
First working demo, on your own data
Fixed
Scope, timeline and price, agreed before we build
Zero
Existing systems replaced